Tunneling

BBT H53

Steinach am Brenner – Tirol, Austria / 05.2023 - 03.2029

The Brenner Base Tunnel (BBT) is the centrepiece of the SCAN-MED Corridor (Scandinavia–Mediterranean), the longest north-south link running through the heart of Europe from Helsinki to Valletta. This trans-European transport link connects the urban centres of Finland, Sweden, Denmark, Germany, Austria and Italy with the ports in Scandinavia and the Mediterranean. It crosses the natural barrier of the Alps over a distance of approximately 55 km from Innsbruck to Franzensfeste.

A view of the TBM’s cutting wheel; in the foreground, a worker in protective clothing is carrying out welding work on parts lying on the ground
© BBT SE

Facts & Figures


Company

ARGE H53 Brenner Base Tunnel – PORR, Marti

Type

Tunneling

Runtime

05.2023 - 03.2029

Principal
BBT SE

Brenner Base Tunnel H53 – a major project with particular technical challenges

The BBT consists of two single-track main tunnel tubes 70 metres apart, connected by cross-passages at regular intervals of 333 metres. Between the two main tunnel tubes lies a lower-lying exploration and service tunnel. Three emergency stopping points, each with a cross-cavern for technical installations, are planned at intervals of no more than 20 km. Each emergency stopping point is accessed via the cross-cavern through an access tunnel with a maximum gradient of approximately 10 per cent and is accessible by road vehicles.

The scope of work required for the H53 construction project is so varied that it demands the full range of engineering expertise from the tunnel construction specialists:

  • Two tunnel boring machines

  • Conveyor belt formwork from the neighbouring contract section H41, through the contract section to the Padastertal landfill site

  • up to five simultaneous cyclic tunnelling operations

  • 38 cross-passages

  • Construction of the inner linings in the three tunnel tubes and cross-passages, in the emergency stop, in the transfer point and in the access tunnel

 

Each of these tasks could be a project in its own right and keep a construction site team fully occupied. In the H53 project, they were combined with an enormous degree of simultaneous execution. All supply and disposal operations take place via a 4 km-long access tunnel, which descends to a depth of more than 400 m.

Continuous tunnelling

The two TBMs are each approximately 7.5 km long. The internal diameter of the tunnel tubes is 9.04 m. They are constructed using a 40 cm thick, 1.95 m wide, single-sealed universal ring system (ring configuration 6+0 with precast base elements).

The logistics were systematically designed to minimise the number of trips to the tunnel boring machine and to keep traffic in the tunnel to a minimum for other trades. Bulk building materials such as tunnel segments, base stones, expanded clay aggregate and dry mortar were transported underground using specialised lorries fitted with hydraulic braking systems and with a payload of around 60 tonnes.

The tunnel boring machines were supplied via an efficient rail system with an underground loading station. General cargo was transferred from lorries to trains via lorry-lift stations, whilst bulk materials were temporarily stored using silo and conveyor belt systems before being loaded onto wagons. To increase efficiency, the decision was taken not to build a further station; instead, a dual-ring supply system was set up. Each supply train transported the material required for the installation of two tubbing rings.

The use of a twin-shield machine largely prevented deformation caused by the constant tension on the segmented tube due to overlying rock loads. The result was precisely installed segment rings with virtually no misalignment or spalling. Thanks to additional safety measures, the tunnel boring machines could also be safely steered through fault zones.

During the approximately 15.5 km of cyclic tunnelling in the main tunnel, cross-passages and railway service galleries, the method was successfully switched from conventional crown/sidewall and floor tunnelling to full-face excavation using steel-fibre-reinforced shotcrete. This allowed the advantages of conveyor belt shoring with crusher feed and the favourable geological conditions to be utilised to the full.

 

Inner lining construction

With the completion of construction lot H53, the installation of railway equipment in the Brenner Base Tunnel can be finalised. Furthermore, cavities already created in preliminary projects are being fitted with an inner lining. A total of around 56 km of inner lining work is to be carried out.

 

The wide variety of different tunnel cross-sections requires specially developed formwork systems. One example is the transfer point, which enables trains to switch between the two main tubes, thereby creating a traffic-free section for maintenance work. The widening profile gradually reaches a width of up to 22 m. The modular formwork concept consists of an eastern and western parament, as well as a cap formwork that can be adapted to the different profiles. Equally unusual is the lifting platform at the emergency stop. There, a formwork unit for a ventilation tunnel is raised by around 5 m to its working level.

 

Construction site facilities

A comprehensive on-site facility was established above ground to supply and remove materials from the various underground work areas. It comprises:

  • Two mixing plants
  • A processing plant for raw materials from a nearby quarry and from the access tunnel
  • An open-air storage area for tunnel segments
  • A railway connection
  • Silo facilities for expanded clay and dry mortar
  • A high-bay warehouse and an open-air storage area with a crane
  • Water protection facilities
  • Workshops for the maintenance of plant and equipment, as well as
  • a site office and a dormitory with 688 beds for staff and subcontractors, some of which are occupied by two people.

 

The challenging Brenner Base Tunnel project demonstrates not only PORR’s concentrated expertise in tunnel construction, but also the efficient and precise teamwork and collaboration between various trades and companies.

You can find more insights into this major project in the video

3,5 km tief im Berg: So lief 2025 im Brenner Basistunnel #Tunneling #brennerbasistunnel

What ultimately counts in the construction business is successfully completed projects. PORR has many of these.