Concrete slab construction
Wolf 2 â Concrete slab feeder tunnel of the Brenner base tunnel
Innsbruck, Austria /
For the Brenner base tunnel, ĂBA constructed a 3.3 km long single layer concrete slab in the âWolf 2â feeder tunnel in March and April 2017.
The extreme linear angle of 10% and the extremely constricted space in the tunnel were major challenges for the ĂBA team.
Facts & Figures
Company
ĂBA â Ăsterreichische Betondecken Ausbau GmbH
Type
Concrete slab construction
Top performance under difficult conditions.
In addition, the works had to be carried out in a single layer execution with a very high slab thickness of 30 cm. All that in a short construction time and under strict terms by the customer.
Further Facts
Wolf 2 â Concrete slab feeder tunnel of the Brenner base tunnel
- Service duration
- 03.2017 - 04.2017