FRS Schmittentunnel North
Zell am See, Austria / 04.2024 - 03.2026
The first section of the escape and rescue tunnel was completed in just under two years.
Facts & Figures
Company
PORR Bau GmbH
Type
Tunneling
Runtime
04.2024 - 03.2026
Schmittentunnel escape and rescue tunnel for greater safety
Described by the Province of Salzburg as the âlittle brotherâ of the main tunnel â which is twice its size â the tunnel has been enhancing safety for road users in the main tunnel ever since the construction work was completed.
In total, PORR carried out the following works in the North contract section:
- 1,770 m of NATM tunnelling in the small cross-section of the escape tunnel, involving around 83,000 mÂł of excavated material
- Excavation of five new cross-passages in the existing road tunnel
- Paving and road surface installation throughout the entire tunnel system
The severely limited space in the portal area of the existing SeehĂ€usl escape tunnel posed a particular challenge during the execution of the works. The construction contract was also unusual, as it was an âalliance contract lightâ that focused solely on the execution of the construction works.
Despite these challenges, PORR was able to complete the project efficiently and on schedule with its experienced team of regional specialists.